| Item |
Tasks |
Description |
Quantity |
Delivery |
Effective Date of Contract (EDOC) |
| 1 |
1.1 |
Meet with Project Officer (PO) and others to further develop work plan; prepare and submit minutes of discussion |
-- |
2 week from EDOC |
|
| 2 |
1.2 |
Submit Monthly Progress Reports |
5 (4 hardcopy and 1 electronic)
508 compliant |
Monthly - 10 days after the end of the month |
|
| 3 |
1.3 |
Hold monthly conference call with TOO |
|
Monthly - 10 days after the end of the month |
|
| 4 |
1.4 |
Submit Revised Work Plan |
5 (4 hardcopy and 1 electronic) |
4 weeks from EDOC |
|
| 5 |
2.1 |
Submit final nominations for TEP |
1 electronic copy |
4 weeks from EDOC |
|
| 6 |
3.1.1 |
Hold first TEP meeting |
|
16 weeks from EDOC |
|
| 7 |
3.1.2 |
Submit report of first TEP meeting |
5 (4 hardcopy and 1 electronic) |
2 weeks from TEP meeting 1 |
|
| 6 |
3.2.1 |
Hold second TEP meeting |
|
28 weeks from EDOC |
|
| 7 |
3.2.2 |
Submit report of second TEP meeting |
5 (4 hardcopy and 1 electronic) |
2 weeks from TEP meeting 2 |
|
| 8 |
3.3.1 |
Hold third TEP meeting |
|
42 weeks from EDOC |
|
| 9 |
3.3.1 |
Submit report of third TEP meeting |
5 (4 hardcopy and 1 electronic) |
2 weeks from TEP meeting 3 |
|
| 10 |
4.1 |
Submit draft list of diverse and representative PSPs organized according to draft framework/taxonomy |
|
8 weeks from EDOC |
|
| 13 |
4.1 |
Submit REVISED draft list of diverse and representative PSPs organized according to draft framework/taxonomy (based on TEP meeting and AHRQ input) |
|
18 weeks from EDOC |
|
| 14 |
5.1 |
Submit draft list of research/evaluation designs and methods to AHRQ |
5 (4 hardcopy and 1 electronic) |
10 weeks from EDOC |
|
| 15 |
5.2 |
Submit revised list of designs and methods to AHRQ based on TEP discussion |
5 (4 hardcopy and 1 electronic) |
18 weeks from EDOC |
|
| 16 |
6.1 |
Submit draft full set of criteria |
5 (4 hardcopy and 1 electronic) |
36 weeks from EDOC |
|
| 17 |
6.1 |
Submit Revised Evidence Assessment criteria, based on TEP discussion |
5 (4 hardcopy and 1 electronic) |
44 weeks from EDOC |
|
| 18 |
7.1 |
Submit Final Draft Report to AHRQ |
5 (4 hardcopy and 1 electronic) |
48 weeks from EDOC |
|
| 23 |
7.2 |
Present project finding to AHRQ |
-- |
50 weeks from EDOC |
|
| 24 |
7.3 |
Submit Final Reports and Final Product |
5 (4 hardcopy and 1 electronic) plus camera ready copy of materials to be printed by AHRQ |
52 weeks from EDOC |
|